Ok, it's been about a month since the last update. These pics were took last week from ground level from a bunch of different angles. The job is coming along good. Thankfully there have been NO deaths to report and everyone is going home w/ all their attachments!!
There has been a lot of work going on, trying to build a bunch of offices on site below the Pillie Tower (main casino tower). The plan is to tear down the million dollar offices and sales center behind the NYNY. This is where City Center 2 is supposed to be built after CC 1 is complete. I have heard that total cost will be around 23 Billion bucks!
OK, the pics aren't too big but there is about a dozen or so, so it may take a few mins to load..... OK, there are more than a dozen so I will break it down into 2 posting (Pam ) Enjoy!
Harmon Condo
Setting tons of steel
Check out the curved steel
The first pieces of the tram rail are installed
The Mandarin Condo
THE CASINO!
Convention Center